A month after the Hunter super storm closed the Hunter Valley rail network trains are at a standstill again for further maintenance work on the tracks.

  waynes Junior Train Controller

Location: Victoria
A month after the Hunter super storm closed the Hunter Valley rail network trains are at a standstill again for further maintenance work on the tracks.

The latest scheduled shutdown began this morning and continues until Thursday night.

Over the next three days, $20 million worth of maintenance is being carried out on the network from the Port of Newcastle to Narrabri and Ulan.
Rail repairs bring Hunter train network to a standstill

Repairs were completed weeks ago according to artc website.

Sponsored advertisement

  GeordieLadinOz Station Master

A month after the Hunter super storm closed the Hunter Valley rail network trains are at a standstill again for further maintenance work on the tracks.

The latest scheduled shutdown began this morning and continues until Thursday night.

Over the next three days, $20 million worth of maintenance is being carried out on the network from the Port of Newcastle to Narrabri and Ulan.

Repairs were completed weeks ago according to artc website.
waynes
You are correct, ARTC website does say storm repairs were complete weeks ago.

The 2nd paragraph is key here - this is a planned shutdown, planned well before the storms came along with $20M worth of work occurring. This happens on a fairly regular basis each year.

It just so happens to be a month after the storms.