About 13 level crossings are due to be done by end 2021. I can figure our some most likely but I don't get up to 13. Anyone have a better idea of which will be this year. The LXRA pages often talk of 2022 but not much for 2021.
The Edithvale-Chelsea-Bonbeach project itself will be majorly completed by mid-2021. That's 5 level crossings. So what's makes the remaining 8.
The Cherry street one is definitely going to be complete by April 2021. That's another one.
South Gippsland Highway is likely to be complete by 2021, it's another road bridge, and it's well progressed. That's one more.
The Hoppers crossing one is simple, with just a road bridge mostly, should be complete by the end of 2021 at best even with those delays.
Gap road crossing in Sunbury is likely to be completed early in 2021 because it's being done simultaneously as Sunbury line upgrade.
Then you also have Greens road on the Cranbourne line, which already has pillars, very easy to see that done in 2021.
The Glenroy crossing is surprisingly well ahead in the schedule, with the early works almost done, I think major construction later in the year will finish it by the end of 2021.
The two on the Lilydale line also seem very progress at the moment, and wouldn't be surprised if they're delivered at the end of 2021 as well.
I predict the 13 crossings that could be delivered by 2021, which the LXRA is talking about. The talks of 2022 are normally the completion date when all the details are complete, but not just the level crossing removal itself, like the completion of the station build and surrounding fauna and floral and the station car parks etc.