10 should go in 2022, unless there is more 'fast-tracking'; namely
Clyde Rd, Berwick announced as being removed in March
Hallam Rd, Hallam - no date yet
Fitzgerald Rd, Ardeer - no date
Robinsons Rd, Deer Park - no date
Bell St, Preston in October
Murray Rd, Preston in October
Cramer St, Preston in October
Oakover Rd, Preston in October
Glenroy Rd, Glenroy 'by the end' of the year
Gap Rd, Sunbury 'late' 2022
After that in 2023:
Greens Rd, Dandenong South - bridge is close to completion but probably will wait for duplication to be finalised
Neerim Rd, Caulfield
Glen Huntly Rd, Glenhuntly
Mont Albert Rd, Mont Albert
Union Rd, Surrey Hills
These are due 'in 2023-24' at present; once work is well underway they'll be able to give us a more precise date:
McGregor Rd, Pakenham
Racecourse Rd, Pakenham
Main St, Pakenham
Although not an LXRP one'
Barwon Heads Rd, Marshall will be removed 'by'
2023 as well
2024
Station Rd/Mt Derrimut Rd, Deer Park
Camms Rd, Cranbourne
Again, not ,LXRP but worth mentioning;
Surf Coast Hwy, Grovedale and Woods St, South Geelong 'by the end' of 2024
And finally for 2025, assuming it isn't fast-tracked also (unless they can find another source of funding to go on with more)
Webster St, Dandenong
Neil