Time for some celebrationsThis is just rebuilt track - why celebrate this?
'Cos it makes them sound like they're doing something when really not much; the plebeians don't know any different.Time for some celebrationsThis is just rebuilt track - why celebrate this?
And of spinning neglected maintenance as “deferred” maintenance.'Cos it makes them sound like they're doing something when really not much; the plebeians don't know any different.Time for some celebrationsThis is just rebuilt track - why celebrate this?
It's in the same vein as politicians/bureaucrats description of addressing deferred maintenance as an 'upgrade'.
Seems to suggest there are areas on the inland rail route which would have been flooded if the work had been completed?Of course the opponents of the proposed Condamine crossing want you to assume so.
https://t.co/3iMtnhmiVm
Fresh from finishing the 189km Carmichael Rail Network, Martinus has been awarded a new build contract for 570km of Inland Rail track, including North Star to Gowrie (Toowoomba).At least It's an Australian company and no a company connected to the CCP
https://roadsonline.com.au/contract-awarded-for-570-km-inland-rail-project-section/
Fresh from finishing the 189km Carmichael Rail Network, Martinus has been awarded a new build contract for 570km of Inland Rail track, including North Star to Gowrie (Toowoomba).Not until I see them seriously into Narromine - Narrabri (or Nth of the border) will I think they are fair dinkum.
https://roadsonline.com.au/contract-awarded-for-570-km-inland-rail-project-section/
Isn`t Gowrie north of the border?Fresh from finishing the 189km Carmichael Rail Network, Martinus has been awarded a new build contract for 570km of Inland Rail track, including North Star to Gowrie (Toowoomba).Not until I see them seriously into Narromine - Narrabri (or Nth of the border) will I think they are fair dinkum.
https://roadsonline.com.au/contract-awarded-for-570-km-inland-rail-project-section/
They were the people responsable for the Murray Basin project!Fresh from finishing the 189km Carmichael Rail Network, Martinus has been awarded a new build contract for 570km of Inland Rail track, including North Star to Gowrie (Toowoomba).At least It's an Australian company and no a company connected to the CCP
https://roadsonline.com.au/contract-awarded-for-570-km-inland-rail-project-section/
Just examined Illabo and Stockingbingal and nothing started yet.
Subscribers: 7334, 8502, bevans, Big J, Boss, br30453, bruce burrow, cuthbert, Dangersdan707, Daryl, fzr560, Jack Le Lievre, james.au, Nightfire, NSWGR8022, Pressman, RTT_Rules, seb2351, WimbledonW, x31