Public Transport Victoria forum hears call for more Maryborough train services
State Government Commits to Developing Rail Infrastructure for Victoria
Horsham residents to be quizzed about future use of dormant rail corridor land
No choppers here: Malcolm Turnbull takes the train to Geelong
Opposition Leader Matthew Guy backs Melbourne Airport rail link
Jail time for train threats to Vline Staff
Premier Daniel Andrews hears efforts to address Central Goldfields disadvantage, push for more Maryborough trains
The Inland Rail Link Melbourne to Brisbane a Similar Case as the RAA's Bendigo - Geelong Rail Link
North-West Rail Alliance urges more council support amid push for return of Mildura passenger rail
Grampians Rail Trail: Shire calls for community to step up and manage facility
Construction workers are completing the installation of 60-tonne concrete and brick arches into the entrance of the new Arden station, as part of Victoria’s Metro Tunnel Project.
The process began in June with the installation of seven support columns, followed by the construction of a temporary steel frame to provide support to the arches as they are lowered into place.
The first of the arches – designed to reflect North Melbourne’s rich industrial history – was installed in mid-October using a 350-tonne crane. The work is expected to be completed by the end of 2021.
The 15 arches are made from precast concrete lined with more than 100,000 bricks, each one laid by hand. They are made up of 45 individual segments, each weighing up to 60 tonnes.
The arches were built using Victorian bricks at a precast facility in South Australia – the only Australian business of its kind with the capacity to undertake such logistically challenging work.
They are being trucked into the site on flat-bed trailers. Once in place, the arches will rise up to 15m above people as they enter the station from Laurens Street.
Construction is also progressing underground, with the final concrete pours for the station’s platform surfaces almost complete.
In the tunnels between Arden and the State Library Station sites, workers are pouring concrete for the tunnel floor slab and installing equipment such as cable brackets and trays as part of rail tunnel fit out.
The station’s services building is being fitted out internally with walls and mechanical, electrical and plumbing systems. Work continues on collar beams – the concrete structures connecting the edge of the tunnel to the station box – at the station’s eastern end.
The station will be the first destination for Metro Tunnel passengers coming from the west on the Sunbury line and a centrepiece of the planned Arden Precinct – expected to include up to 34,000 jobs and be home to around 15,000 residents by 2050.
Arden Station will create a sustainable transport hub within walking distance of the North Melbourne Recreation Centre, Arden Street Oval and the route 57 tram. It will feature inviting green spaces, wide pedestrian paths, drop-off zones and taxi bays directly outside the station, and more than 120 bike parking spaces.
When finished, the Metro Tunnel is expected to create capacity for more than half a million additional passengers a week during peak times across Melbourne’s train network and provide a future direct link to Melbourne Airport Rail.
Victorian Premier, Daniel Andrews, said, “It’s wonderful to see Arden Station’s brick arches taking shape, creating what will be a landmark for Melbourne’s north, bringing more jobs and more places for Victorians to live.
“The Metro Tunnel team have been working around the clock in 2021 despite the challenges of the pandemic, keeping thousands of Victorians in jobs as we work towards opening a year ahead of schedule in 2025.”
This article first appeared on infrastructuremagazine.com.au
About this website
Railpage version 3.10.0.0037
All logos and trademarks in this site are property of their respective owner. The comments are property of their posters, all the rest is © 2003-2022 Interactive Omnimedia Pty Ltd.
You can syndicate our news using one of the RSS feeds.
Stats for nerds
Gen time: 1.044s | RAM: 6.68kb