Public Transport Victoria forum hears call for more Maryborough train services
State Government Commits to Developing Rail Infrastructure for Victoria
Horsham residents to be quizzed about future use of dormant rail corridor land
No choppers here: Malcolm Turnbull takes the train to Geelong
Opposition Leader Matthew Guy backs Melbourne Airport rail link
Jail time for train threats to Vline Staff
Premier Daniel Andrews hears efforts to address Central Goldfields disadvantage, push for more Maryborough trains
The Inland Rail Link Melbourne to Brisbane a Similar Case as the RAA's Bendigo - Geelong Rail Link
North-West Rail Alliance urges more council support amid push for return of Mildura passenger rail
Grampians Rail Trail: Shire calls for community to step up and manage facility
Work towards rail bridge foundations has now commenced in an inner Melbourne suburb.
Thirty-four piles (deep concrete foundations to support the rail bridge) are being bored at the Toorak Road site in Kooyong.
Piling rigs and cranes have been at work on the site of the level crossing removal project. A piling rig is a specialist piece of equipment with a high mast that enables it to dig deep into the ground.
The piles at Toorak Road will be up to 20 metres deep and 2.1 metres in diameter. The locations of the piles were determined after geotechnical investigations were conducted in late 2018 and early 2019.
Once the piles have been bored, cranes will lift a steel cylindrical ‘cage’ into place to reinforce the pile, with each piling cage weighing between 9 tonnes and 12.5 tonnes. The hole is then reinforced with steel and concrete.
“This process creates secure foundations and ensures safety and stability of the rail bridge,” according to a Victorian government statement.
The post Rail bridge construction underway in Melbourne appeared first on Rail Express.
This article first appeared on www.railexpress.com.au
About this website
Railpage version 3.10.0.0037
All logos and trademarks in this site are property of their respective owner. The comments are property of their posters, all the rest is © 2003-2019 Interactive Omnimedia Pty Ltd.
You can syndicate our news using one of the RSS feeds.
Stats for nerds
Gen time: 0.646s | RAM: 6.5kb